Dept. of Trans. PROGRESS Serial No. Contract No. 23-268-09-03 03-0H08U4 PROGRESS PAYMENT VOUCHER %complete: %time: 75% 73% Location: Federal Project: 03-SAC-50-L0.2/R6.1 NONE Progress payment No. 043 Payment period ending: 09-20-23 FLATIRON WEST, INC. 1200 CONCORD AVENUE #465 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 290,268,935.00 6,071,782.50 2. a. Extra Work 2,263,134.81 69.60 b. Adustment Comp. -540,156.08 0.00 3. Materials on Hand 3,518,533.93 0.00 4. Earned Subject to Retention 295,510,447.66 6,071,852.10 5. Mobilization 6. Total Work Completed 291,991,913.73 7. Deductions -608,513.28 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 294,901,934.38 6,071,852.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,071,852.10