Dept. of Trans. PROGRESS Serial No. Contract No. 23-332-08-43 03-0H08U4 PROGRESS PAYMENT VOUCHER %complete: %time: 78% 77% Location: Federal Project: 03-SAC-50-L0.2/R6.1 NONE Progress payment No. 046 Payment period ending: 11-20-23 FLATIRON WEST, INC. 1200 CONCORD AVENUE #465 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 304,472,617.50 6,990,375.00 2. a. Extra Work 2,375,967.54 0.00 b. Adustment Comp. 459,214.20 -200.00 3. Materials on Hand 3,518,533.93 0.00 4. Earned Subject to Retention 310,826,333.17 6,990,175.00 5. Mobilization 6. Total Work Completed 307,307,799.24 7. Deductions -248,344.80 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 310,577,988.37 6,990,175.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,990,175.00