Dept. of Trans. PROGRESS Serial No. Contract No. 24-019-09-35 03-0H08U4 PROGRESS PAYMENT VOUCHER %complete: %time: 82% 70% Location: Federal Project: 03-SAC-50-L0.2/R6.1 NONE Progress payment No. 049 Payment period ending: 01-20-24 FLATIRON WEST, INC. 1200 CONCORD AVENUE #465 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 316,655,150.00 6,461,072.50 2. a. Extra Work 2,548,109.27 0.00 b. Adustment Comp. 4,295,396.83 -800.00 3. Materials on Hand 3,383,733.93 0.00 4. Earned Subject to Retention 326,882,390.03 6,460,272.50 5. Mobilization 6. Total Work Completed 323,498,656.10 7. Deductions -231,344.80 21,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 326,651,045.23 6,481,272.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,481,272.50