Dept. of Trans. PROGRESS Serial No. Contract No. 24-051-15-22 03-0H08U4 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 70% Location: Federal Project: 03-SAC-50-L0.2/R6.1 NONE Progress payment No. 050 Payment period ending: 02-20-24 FLATIRON WEST, INC. 1200 CONCORD AVENUE #465 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 320,479,797.50 3,824,647.50 2. a. Extra Work 2,555,656.40 7,547.13 b. Adustment Comp. 4,294,796.83 -600.00 3. Materials on Hand 3,383,733.93 0.00 4. Earned Subject to Retention 330,713,984.66 3,831,594.63 5. Mobilization 6. Total Work Completed 327,330,250.73 7. Deductions -505,689.80 -274,345.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 330,208,294.86 3,557,249.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,557,249.63