Dept. of Trans. PROGRESS Serial No. Contract No. 24-082-13-42 03-0H08U4 PROGRESS PAYMENT VOUCHER %complete: %time: 84% 70% Location: Federal Project: 03-SAC-50-L0.2/R6.1 NONE Progress payment No. 051 Payment period ending: 03-20-24 FLATIRON WEST, INC. 1200 CONCORD AVENUE #465 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 324,558,602.50 4,078,805.00 2. a. Extra Work 2,575,006.40 19,350.00 b. Adustment Comp. 4,293,846.83 -950.00 3. Materials on Hand 3,335,646.99 -48,086.94 4. Earned Subject to Retention 334,763,102.72 4,049,118.06 5. Mobilization 6. Total Work Completed 331,427,455.73 7. Deductions -510,689.80 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 334,252,412.92 4,044,118.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,044,118.06