Dept. of Trans. PROGRESS Serial No. Contract No. 24-109-12-26 03-0H08U4 PROGRESS PAYMENT VOUCHER %complete: %time: 85% 71% Location: Federal Project: 03-SAC-50-L0.2/R6.1 NONE Progress payment No. 052 Payment period ending: 04-20-24 FLATIRON WEST, INC. 1200 CONCORD AVENUE #465 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 328,666,465.00 4,107,862.50 2. a. Extra Work 2,575,006.40 0.00 b. Adustment Comp. 4,292,676.83 -1,170.00 3. Materials on Hand 3,203,460.10 -132,186.89 4. Earned Subject to Retention 338,737,608.33 3,974,505.61 5. Mobilization 6. Total Work Completed 335,534,148.23 7. Deductions -513,689.80 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 338,223,918.53 3,971,505.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,971,505.61