Dept. of Trans. PROGRESS Serial No. Contract No. 24-149-11-27 03-0H08U4 PROGRESS PAYMENT VOUCHER %complete: %time: 85% 73% Location: Federal Project: 03-SAC-50-L0.2/R6.1 NONE Progress payment No. 053 Payment period ending: 05-20-24 FLATIRON WEST, INC. 1200 CONCORD AVENUE #465 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 333,852,885.00 5,186,420.00 2. a. Extra Work 2,575,006.40 0.00 b. Adustment Comp. 4,292,526.83 -150.00 3. Materials on Hand 5,960,130.89 2,756,670.79 4. Earned Subject to Retention 346,680,549.12 7,942,940.79 5. Mobilization 6. Total Work Completed 340,720,418.23 7. Deductions -523,689.80 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 346,156,859.32 7,932,940.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,932,940.79