Dept. of Trans. PROGRESS Serial No. Contract No. 24-295-07-43 03-0H08U4 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 82% Location: Federal Project: 03-SAC-50-L0.2/R6.1 NONE Progress payment No. 058 Payment period ending: 10-20-24 FLATIRON WEST, INC. 1200 CONCORD AVENUE #465 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 354,464,890.00 4,073,307.50 2. a. Extra Work 3,064,800.44 0.00 b. Adustment Comp. 4,271,406.83 -100.00 3. Materials on Hand 5,744,519.99 -215,610.90 4. Earned Subject to Retention 367,545,617.26 3,857,596.60 5. Mobilization 6. Total Work Completed 361,801,097.27 7. Deductions -513,689.80 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 367,031,927.46 3,847,596.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,847,596.60