Dept. of Trans. PROGRESS Serial No. Contract No. 24-330-15-09 03-0H08U4 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 75% Location: Federal Project: 03-SAC-50-L0.2/R6.1 NONE Progress payment No. 059 Payment period ending: 11-20-24 FLATIRON WEST, INC. 1200 CONCORD AVENUE #465 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 356,891,215.00 2,426,325.00 2. a. Extra Work 3,064,800.44 0.00 b. Adustment Comp. 35,748,881.43 31,477,474.60 3. Materials on Hand 5,498,198.46 -246,321.53 4. Earned Subject to Retention 401,203,095.33 33,657,478.07 5. Mobilization 6. Total Work Completed 395,704,896.87 7. Deductions -523,689.80 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 400,679,405.53 33,647,478.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 33,647,478.07