Dept. of Trans. PROGRESS Serial No. Contract No. 25-108-15-06 03-0H08U4 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 80% Location: Federal Project: 03-SAC-50-L0.2/R6.1 NONE Progress payment No. 064 Payment period ending: 04-20-25 FLATIRON WEST, INC. 1200 CONCORD AVENUE #465 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 368,043,837.50 1,329,882.50 2. a. Extra Work 3,584,669.27 0.00 b. Adustment Comp. 44,511,098.88 -25,000.00 3. Materials on Hand 5,570,617.71 0.00 4. Earned Subject to Retention 421,710,223.36 1,304,882.50 5. Mobilization 6. Total Work Completed 416,139,605.65 7. Deductions -517,689.80 4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 421,192,533.56 1,308,882.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,308,882.50