Dept. of Trans. PROGRESS Serial No. Contract No. 25-203-06-35 03-0H08U4 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 84% Location: Federal Project: 03-SAC-50-L0.2/R6.1 NONE Progress payment No. 067 Payment period ending: 07-20-25 FLATIRON DRAGADOS WEST LLC 1200 CONCORD AVE #465 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 372,877,420.00 1,892,690.00 2. a. Extra Work 4,043,417.40 0.00 b. Adustment Comp. 44,510,998.88 -100.00 3. Materials on Hand 4,097,700.48 -1,287,681.96 4. Earned Subject to Retention 425,529,536.76 604,908.04 5. Mobilization 6. Total Work Completed 421,431,836.28 7. Deductions -513,689.80 -4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 425,015,846.96 600,908.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 600,908.04