Dept. of Trans. PROGRESS Serial No. Contract No. 25-261-10-36 03-0H08U4 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 88% Location: Federal Project: 03-SAC-50-L0.2/R6.1 NONE Progress payment No. 069 Payment period ending: 09-20-25 FLATIRON DRAGADOS WEST LLC 1200 CONCORD AVE #465 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 376,856,850.00 1,905,340.00 2. a. Extra Work 4,428,068.99 83,452.39 b. Adustment Comp. 45,173,833.02 -400.00 3. Materials on Hand 3,236,103.97 -329,844.64 4. Earned Subject to Retention 429,694,855.98 1,658,547.75 5. Mobilization 6. Total Work Completed 426,458,752.01 7. Deductions -297,181.05 16,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 429,397,674.93 1,674,547.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,674,547.75