Dept. of Trans. PROGRESS Serial No. Contract No. 25-328-06-42 03-0H08U4 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 90% Location: Federal Project: 03-SAC-50-L0.2/R6.1 NONE Progress payment No. 071 Payment period ending: 11-20-25 FLATIRON DRAGADOS WEST LLC 1200 CONCORD AVE #465 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 380,940,310.00 2,499,210.00 2. a. Extra Work 4,594,002.32 29,400.00 b. Adustment Comp. 44,401,747.18 -226,059.09 3. Materials on Hand 1,702,693.18 -1,533,410.79 4. Earned Subject to Retention 431,638,752.68 769,140.12 5. Mobilization 6. Total Work Completed 429,936,059.50 7. Deductions -313,181.05 -6,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 431,325,571.63 763,140.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 763,140.12