Dept. of Trans. PROGRESS Serial No. Contract No. 21-236-15-21 03-0H10U4 PROGRESS PAYMENT VOUCHER %complete: %time: 80% 61% Location: Federal Project: 03-SAC-5-9.7/24.9 B1IM-005-6(349) Progress payment No. 027 Payment period ending: 08-20-21 NOR CAL PAVING PO BOX 15002 SACRAMENTO CA 95851 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 156,552,914.58 17,391,498.99 2. a. Extra Work 4,337,503.33 0.00 b. Adustment Comp. 23,674,134.34 0.00 3. Materials on Hand 964,071.90 0.00 4. Earned Subject to Retention 185,528,624.15 17,391,498.99 5. Mobilization 30,000,000.00 0.00 6. Total Work Completed 214,564,552.25 7. Deductions -2,587,214.00 -15,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 212,941,410.15 17,376,498.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 17,376,498.99