Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 21-251-15-29 03-0H10U4 PROGRESS PAYMENT VOUCHER %complete: %time: 75% 61% Location: Federal Project: 03-SAC-5-9.7/24.9 B1IM-005-6(349) Progress payment No. 028 Payment period ending: 08-20-21 NOR CAL PAVING PO BOX 15002 SACRAMENTO CA 95851 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 156,916,883.05 363,968.47 2. a. Extra Work 5,055,583.95 718,080.62 b. Adustment Comp. 23,674,134.34 0.00 3. Materials on Hand 964,071.90 0.00 4. Earned Subject to Retention 186,610,673.24 1,082,049.09 5. Mobilization 30,000,000.00 0.00 6. Total Work Completed 215,646,601.34 7. Deductions -2,587,214.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 214,023,459.24 1,082,049.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,082,049.09