Dept. of Trans. PROGRESS Serial No. Contract No. 21-263-16-47 03-0H10U4 PROGRESS PAYMENT VOUCHER %complete: %time: 78% 65% Location: Federal Project: 03-SAC-5-9.7/24.9 B1IM-005-6(349) Progress payment No. 029 Payment period ending: 09-20-21 NOR CAL PAVING PO BOX 15002 SACRAMENTO CA 95851 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 166,279,331.53 9,362,448.51 2. a. Extra Work 5,055,583.95 0.00 b. Adustment Comp. 24,683,086.94 1,008,952.60 3. Materials on Hand 1,777,618.89 813,546.99 4. Earned Subject to Retention 197,795,621.31 11,184,948.10 5. Mobilization 30,000,000.00 0.00 6. Total Work Completed 226,018,002.42 7. Deductions -2,577,214.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 225,218,407.31 11,194,948.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 11,194,948.10