Dept. of Trans. PROGRESS Serial No. Contract No. 24-019-14-49 03-0H1614 PROGRESS PAYMENT VOUCHER %complete: %time: 75% 56% Location: Federal Project: 03-YUB-70-14.8/15.7 ACNH-P070(147) Progress payment No. 006 Payment period ending: 01-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,291,982.26 930,238.48 2. a. Extra Work 78,804.67 300.00 b. Adustment Comp. 3. Materials on Hand 0.00 -24,164.00 4. Earned Subject to Retention 7,370,786.93 906,374.48 5. Mobilization 1,310,704.91 0.00 6. Total Work Completed 8,681,491.84 7. Deductions -183,248.40 21,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,498,243.44 927,374.48 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 927,374.48