Dept. of Trans. PROGRESS Serial No. Contract No. 24-142-09-31 03-0H1614 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 94% Location: Federal Project: 03-YUB-70-14.8/15.7 ACNH-P070(147) Progress payment No. 010 Payment period ending: 05-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,720,630.89 738,563.76 2. a. Extra Work 135,876.10 0.00 b. Adustment Comp. 3. Materials on Hand 0.00 -93,838.94 4. Earned Subject to Retention 9,856,506.99 644,724.82 5. Mobilization 1,310,704.91 0.00 6. Total Work Completed 11,167,211.90 7. Deductions -179,248.40 3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,987,963.50 647,724.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 647,724.82