Dept. of Trans. PROGRESS Serial No. Contract No. 19-204-11-08 03-0H2204 PROGRESS PAYMENT VOUCHER %complete: %time: 38% 53% Location: Federal Project: 03-NEV-49-7.4/R14.5 B1NH-P049(178) Progress payment No. 002 Payment period ending: 07-20-19 CENTRAL COAST FINANCIAL GROUP INC 393 MORNING STAR DR SONORA CA 95370 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 396,254.45 213,295.45 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 396,254.45 213,295.45 5. Mobilization 142,500.00 30,000.00 6. Total Work Completed 538,754.45 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 538,754.45 243,295.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 243,295.45