Dept. of Trans. SEMI-FINAL Serial No. Contract No. 22-025-16-22 03-0H3424 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-SAC-99-21.9/23.6 NONE Progress payment No. 006 Payment period ending: 10-08-21 BRIDGEWAY CIVIL CONSTRUCTORS INC 3333 VACA VALLEY PKWY #2000 B VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,218,682.25 0.00 2. a. Extra Work 720,796.58 195,757.49 b. Adustment Comp. -5,668.50 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,933,810.33 195,757.49 5. Mobilization 270,000.00 0.00 6. Total Work Completed 4,203,810.33 7. Deductions -11,000.00 340,800.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,192,810.33 536,557.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 536,557.49