Dept. of Trans. PROGRESS Serial No. Contract No. 24-261-11-48 03-0H3704 PROGRESS PAYMENT VOUCHER %complete: %time: 63% 14% Location: Federal Project: 03-YUB-65-R0.5/1.8 NONE Progress payment No. 005 Payment period ending: 09-20-24 KNIFE RIVER CONSTRUCTION 1764 SKYWAY CHICO CA 95928 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,086,614.88 715,485.52 2. a. Extra Work b. Adustment Comp. -116,235.00 -116,235.00 3. Materials on Hand 0.00 -68,191.00 4. Earned Subject to Retention 3,970,379.88 531,059.52 5. Mobilization 300,000.00 0.00 6. Total Work Completed 4,270,379.88 7. Deductions -3,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,267,379.88 531,059.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 531,059.52