Dept. of Trans. PROGRESS Serial No. Contract No. 24-295-09-58 03-0H3704 PROGRESS PAYMENT VOUCHER %complete: %time: 66% 17% Location: Federal Project: 03-YUB-65-R0.5/1.8 NONE Progress payment No. 006 Payment period ending: 10-20-24 KNIFE RIVER CONSTRUCTION 1764 SKYWAY CHICO CA 95928 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,325,722.63 239,107.75 2. a. Extra Work b. Adustment Comp. -116,235.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,209,487.63 239,107.75 5. Mobilization 300,000.00 0.00 6. Total Work Completed 4,509,487.63 7. Deductions -13,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,496,487.63 229,107.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 229,107.75