Dept. of Trans. PROGRESS Serial No. Contract No. 23-080-13-56 03-0H6704 PROGRESS PAYMENT VOUCHER %complete: %time: 0% 0% Location: Federal Project: 03-SAC-99-12.7/24.3 ACNH-X067(84) Progress payment No. 001 Payment period ending: 03-20-23 ALFARO COMMUNICATIONS CONSTRUCTION INC 15614 S. ATLANTIC AVENUE COMPTON CA 90221 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 40,941.50 40,941.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 40,941.50 40,941.50 5. Mobilization 6. Total Work Completed 40,941.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 40,941.50 40,941.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 40,941.50