Dept. of Trans. PROGRESS Serial No. Contract No. 20-325-08-08 03-0H6804 PROGRESS PAYMENT VOUCHER %complete: %time: 10% 38% Location: Federal Project: 03-BUT-70-13.4/18.9 SNHG-000C(521) Progress payment No. 001 Payment period ending: 11-20-20 DIRT AND AGGREGATE INTERCHANGE INC. 20905 NE SANDY BLVD FAIRVIEW OR 97024 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 82,331.20 82,331.20 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 82,331.20 82,331.20 5. Mobilization 50,000.00 50,000.00 6. Total Work Completed 132,331.20 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 132,331.20 132,331.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 132,331.20