Dept. of Trans. PROGRESS Serial No. Contract No. 22-110-11-16 03-0H6904 PROGRESS PAYMENT VOUCHER %complete: %time: 47% 18% Location: Federal Project: 03-NEV-999 NONE Progress payment No. 002 Payment period ending: 04-20-22 TEICHERT CONSTRUCTION 3500 AMERICAN RIVER DRIVE SACRAMENTO CA 95864 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 414,578.50 294,615.50 2. a. Extra Work b. Adustment Comp. -6,331.75 -6,331.75 3. Materials on Hand 4. Earned Subject to Retention 408,246.75 288,283.75 5. Mobilization 90,250.00 19,000.00 6. Total Work Completed 498,496.75 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 488,496.75 297,283.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 297,283.75