Dept. of Trans. PROGRESS Serial No. Contract No. 22-139-13-21 03-0H6904 PROGRESS PAYMENT VOUCHER %complete: %time: 63% 35% Location: Federal Project: 03-NEV-999 NONE Progress payment No. 003 Payment period ending: 05-20-22 TEICHERT CONSTRUCTION 3500 AMERICAN RIVER DRIVE SACRAMENTO CA 95864 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 581,040.30 166,461.80 2. a. Extra Work b. Adustment Comp. -6,331.75 0.00 3. Materials on Hand 4. Earned Subject to Retention 574,708.55 166,461.80 5. Mobilization 95,000.00 4,750.00 6. Total Work Completed 669,708.55 7. Deductions -5,000.00 5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 664,708.55 176,211.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 176,211.80