Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 22-278-08-00 03-0H6904 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-NEV-999 NONE Progress payment No. 006 Payment period ending: 08-23-22 TEICHERT CONSTRUCTION 3500 AMERICAN RIVER DRIVE SACRAMENTO CA 95864 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 876,798.25 0.00 2. a. Extra Work 27,982.15 27,982.15 b. Adustment Comp. 2,492.16 8,823.91 3. Materials on Hand 4. Earned Subject to Retention 907,272.56 36,806.06 5. Mobilization 95,000.00 0.00 6. Total Work Completed 1,002,272.56 7. Deductions -25,000.00 -20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 977,272.56 16,806.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 16,806.06