Dept. of Trans. PROGRESS Serial No. Contract No. 21-117-10-12 03-0H7204 PROGRESS PAYMENT VOUCHER %complete: %time: 11% 11% Location: Federal Project: 03-PLA-80-1.3/63.5 SIMG-804(334) Progress payment No. 001 Payment period ending: 04-20-21 HIGHWAY SPECIALTY COMPANY INC 6591 EASTSIDE RD REDDING CA 96001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 243,634.50 243,634.50 2. a. Extra Work b. Adustment Comp. 4,340.00 4,340.00 3. Materials on Hand 313,285.83 313,285.83 4. Earned Subject to Retention 561,260.33 561,260.33 5. Mobilization 51,300.00 51,300.00 6. Total Work Completed 299,274.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 612,560.33 612,560.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 612,560.33