Dept. of Trans. PROGRESS Serial No. Contract No. 20-023-12-52 03-0J1004 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 3% Location: Federal Project: 03-VAR NONE Progress payment No. 003 Payment period ending: 01-20-20 LAMON CONSTRUCTION CO INC 871 VON GELDERN WAY YUBA CITY CA 95991 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 992,430.72 13,205.69 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 992,430.72 13,205.69 5. Mobilization 6. Total Work Completed 992,430.72 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 992,430.72 13,205.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 13,205.69