Dept. of Trans. PROGRESS Serial No. Contract No. 22-202-09-30 03-0J2504 PROGRESS PAYMENT VOUCHER %complete: %time: 62% 69% Location: Federal Project: 03-PLA-28-10.2/10.2 NONE Progress payment No. 003 Payment period ending: 07-20-22 MARTIN BROTHERS CONSTRUCTION 8801 FOLSOM BLVD #260 SACRAMENTO CA 95826 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 517,133.08 258,281.08 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 517,133.08 258,281.08 5. Mobilization 6. Total Work Completed 517,133.08 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 507,133.08 248,281.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 248,281.08