Dept. of Trans. PROGRESS Serial No. Contract No. 20-111-14-03 03-0J2604 PROGRESS PAYMENT VOUCHER %complete: %time: 85% 100% Location: Federal Project: 03-SAC-5 NONE 03-YOL-5 Progress payment No. 001 Payment period ending: 02-19-20 THE DUTRA GROUP 2350 KERNER BLVD #200 SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 328,441.81 328,441.81 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 328,441.81 328,441.81 5. Mobilization 6. Total Work Completed 328,441.81 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 328,441.81 328,441.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 328,441.81