Dept. of Trans. PROGRESS Serial No. Contract No. 26-264-07-32 03-0J5204 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 39% Location: Federal Project: 03-VAR ACNH-P020(204) Progress payment No. 005 Payment period ending: 09-20-26 BALDWIN CONTRACTING CO INC 1764 SKYWAY CHICO CA 95928 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,590,224.63 1,600,304.80 2. a. Extra Work 206,665.67 143,311.15 b. Adustment Comp. 1,650.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 11,798,540.30 1,743,615.95 5. Mobilization 1,250,000.00 0.00 6. Total Work Completed 13,048,540.30 7. Deductions -28,000.00 -8,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,020,540.30 1,735,615.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,735,615.95