Dept. of Trans. PROGRESS Serial No. Contract No. 26-110-08-39 03-0J5504 PROGRESS PAYMENT VOUCHER %complete: %time: 7% 5% Location: Federal Project: 03-PLA-80-50.7 NONE Progress payment No. 002 Payment period ending: 04-20-26 MCCUEN CONSTRUCTION INC 3269 SWETZER RD LOOMIS CA 95650 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 880,560.87 880,560.87 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 185,860.00 0.00 4. Earned Subject to Retention 1,066,420.87 880,560.87 5. Mobilization 6. Total Work Completed 880,560.87 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,066,420.87 880,560.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 880,560.87