Dept. of Trans. PROGRESS Serial No. Contract No. 26-237-11-12 03-0J6204 PROGRESS PAYMENT VOUCHER %complete: %time: 12% 0% Location: Federal Project: 03-VAR PTNH-X067(85) Progress payment No. 002 Payment period ending: 08-20-26 THOMPSON BUILDERS CORPORATION 5400 HANNA RANCH RD NOVATO CA 94945 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 881,662.64 564,247.77 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 881,662.64 564,247.77 5. Mobilization 600,000.00 600,000.00 6. Total Work Completed 1,481,662.64 7. Deductions -1,000.00 5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,480,662.64 1,169,247.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,169,247.77