Dept. of Trans. PROGRESS Serial No. Contract No. 22-202-10-11 03-0J7204 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 100% Location: Federal Project: 03-BUT-70-39.3/39.3 STER-37Y6(4) Progress payment No. 005 Payment period ending: 07-20-22 SERAFIX ENGINEERING CONTRACTORS INC 7 CROW CANYON CT #250 SAN RAMON CA 94583 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,614,814.99 20,900.00 2. a. Extra Work 146,575.46 94,075.46 b. Adustment Comp. -13,642.91 -13,642.91 3. Materials on Hand 4. Earned Subject to Retention 1,747,747.54 101,332.55 5. Mobilization 6. Total Work Completed 1,747,747.54 7. Deductions -13,000.00 -13,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,734,747.54 88,332.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 88,332.55