Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 24-304-11-00 03-0L2404 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-PLA-80-448.0/58.7 NONE Progress payment No. 012 Payment period ending: 08-21-24 FBD VANGUARD CONSTRUCTION INC 550 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 72,731.00 72,731.00 2. a. Extra Work 14,711,851.92 59,544.40 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 14,784,582.92 132,275.40 5. Mobilization 6. Total Work Completed 14,784,582.92 7. Deductions -30,000.00 -18,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,754,582.92 114,275.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 114,275.40