Dept. of Trans. PROGRESS Serial No. Contract No. 24-122-13-12 03-0N3504 PROGRESS PAYMENT VOUCHER %complete: %time: 0% 2% Location: Federal Project: 03-SAC-5-250.0/28.0 NONE Progress payment No. 001 Payment period ending: 04-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 43,285.13 43,285.13 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 43,285.13 43,285.13 5. Mobilization 6. Total Work Completed 43,285.13 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 43,285.13 43,285.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 43,285.13