Dept. of Trans. PROGRESS Serial No. Contract No. 24-353-09-52 03-0N7904 PROGRESS PAYMENT VOUCHER %complete: %time: 74% 98% Location: Federal Project: 03-BUT-70-350.0/36.0 NONE Progress payment No. 006 Payment period ending: 12-20-24 BALDWIN CONTRACTING CO INC 1764 SKYWAY CHICO CA 95928 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 551,524.35 26,130.34 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 551,524.35 26,130.34 5. Mobilization 6. Total Work Completed 551,524.35 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 551,524.35 26,130.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 26,130.34