Dept. of Trans. PROGRESS Serial No. Contract No. 10-081-15-01 03-1A1404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 10% 5% 03-SAC-51-6.0/8.3 Federal Project: NONE Progress payment No. 02 Payment period ending: 03-22-10 WATKIN AND BORTOLUSSI INC 77 LARKSPUR STREET SAN RAFAEL CA 949014820 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 58,125.00 6,375.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 27,402.13 4,455.44 4. Earned Subject to Retention 85,527.13 10,830.44 5. Mobilization 63,500.00 0.00 6. Total Work Completed 121,625.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 149,027.13 10,830.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,830.44