Dept. of Trans. PROGRESS Serial No. Contract No. 02-053-11-48 03-1A1814 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 22% 3% 03-SAC-5-21.8/23.8 Federal Project: ACIM-3067(16) Progress payment No. 01 Payment period ending: 02-20-02 TERRA CAL CONSTRUCTION INC 401 C RAILROAD AVE SUISUN CITY CA 94585 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 107,502.04 107,502.04 2.a. Extra Work b. Adjustment Comp. 22,962.00 22,962.00 3. Materials on Hand 18,450.40 18,450.40 4. Earned Subject to Retention 148,914.44 148,914.44 5. Mobilization 114,684.75 114,684.75 6. Total Work Completed 245,148.79 7. Deductions -31,589.78 -31,589.78 8. a.Contract Retentions -14,891.44 -14,891.44 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 217,117.97 217,117.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 217,117.97