Dept. of Trans. PROGRESS Serial No. Contract No. 02-169-11-24 03-1A1814 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 54% 11% 03-SAC-5-21.8/23.8 Federal Project: ACIM-3067(16) Progress payment No. 05 Payment period ending: 06-20-02 TERRA CAL CONSTRUCTION INC 401 C RAILROAD AVE SUISUN CITY CA 94585 Escrow No. 01918 Total Estimate This Estimate 1. Contract Itms Without Mobil. 447,987.07 19,388.54 2.a. Extra Work b. Adjustment Comp. 22,962.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 470,949.07 19,388.54 5. Mobilization 145,267.35 0.00 6. Total Work Completed 616,216.42 7. Deductions -40,013.72 0.00 8. a.Contract Retentions -23,547.45 -969.42 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 552,655.25 18,419.12 10. Reduction Amt to Escrow 11. Payment to Escrow 23,540.00 12. Net Pymt. this Estimate 18,419.12