Dept. of Trans. PROGRESS Serial No. Contract No. 03-169-12-57 03-1A1814 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 80% 37% 03-SAC-5-21.8/23.8 Federal Project: ACIM-3067(16) Progress payment No. 18 Payment period ending: 06-20-03 TERRA CAL CONSTRUCTION INC 401 C RAILROAD AVE SUISUN CITY CA 94585 Escrow No. 01918 Total Estimate This Estimate 1. Contract Itms Without Mobil. 752,608.58 7,306.67 2.a. Extra Work 10,582.78 1,654.21 b. Adjustment Comp. 25,236.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 788,427.36 8,960.88 5. Mobilization 152,913.00 0.00 6. Total Work Completed 941,340.36 7. Deductions -47,119.71 0.00 8. a.Contract Retentions -39,421.37 -448.05 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 854,799.28 8,512.83 10. Reduction Amt to Escrow 11. Payment to Escrow 39,420.00 12. Net Pymt. this Estimate 8,512.83