Dept. of Trans. PROGRESS Serial No. Contract No. 04-296-10-10 03-1A1814 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 72% 03-SAC-5-21.8/23.8 Federal Project: ACIM-3067(16) Progress payment No. 34 Payment period ending: 10-20-04 TERRA CAL CONSTRUCTION INC 14530 JOANBRIDGE ST BALDWIN PARK CA 91706 Escrow No. 01918 Total Estimate This Estimate 1. Contract Itms Without Mobil. 877,295.74 7,306.67 2.a. Extra Work 12,761.78 0.00 b. Adjustment Comp. 25,236.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 915,293.52 7,306.67 5. Mobilization 152,913.00 0.00 6. Total Work Completed 1,068,206.52 7. Deductions -42,119.71 0.00 8. a.Contract Retentions -45,764.68 -365.34 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 980,322.13 6,941.33 10. Reduction Amt to Escrow 11. Payment to Escrow 45,760.00 12. Net Pymt. this Estimate 6,941.33