Dept. of Trans. PROGRESS Serial No. Contract No. 04-357-09-14 03-1A1814 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 76% 03-SAC-5-21.8/23.8 Federal Project: ACIM-3067(16) Progress payment No. 36 Payment period ending: 12-20-04 TERRA CAL CONSTRUCTION INC 30765 PACIFIC COAST HIWAY 365 MALIBU CA 90265 Escrow No. 01918 Total Estimate This Estimate 1. Contract Itms Without Mobil. 891,909.08 7,306.67 2.a. Extra Work 12,761.78 0.00 b. Adjustment Comp. 25,236.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 929,906.86 7,306.67 5. Mobilization 152,913.00 0.00 6. Total Work Completed 1,082,819.86 7. Deductions -42,119.71 0.00 8. a.Contract Retentions -46,495.34 -365.33 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 994,204.81 6,941.34 10. Reduction Amt to Escrow 11. Payment to Escrow 46,490.00 12. Net Pymt. this Estimate 6,941.34