Dept. of Trans. PROGRESS Serial No. Contract No. 05-299-14-16 03-1A1814 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 98% 03-SAC-5-21.8/23.8 Federal Project: ACIM-3067(16) Progress payment No. 46 Payment period ending: 10-20-05 TERRA CAL CONSTRUCTION INC 40255 98TH ST. WEST LEONA VALLEY, CA 93551 Escrow No. 01918 Total Estimate This Estimate 1. Contract Itms Without Mobil. 946,742.98 552.20 2.a. Extra Work 18,813.42 0.00 b. Adjustment Comp. 25,236.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 990,792.40 552.20 5. Mobilization 152,913.00 0.00 6. Total Work Completed 1,143,705.40 7. Deductions -42,119.71 0.00 8. a.Contract Retentions -49,539.62 -27.61 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,052,046.07 524.59 10. Reduction Amt to Escrow 11. Payment to Escrow 49,530.00 12. Net Pymt. this Estimate 524.59