Dept. of Trans. PROGRESS Serial No. Contract No. 11-294-14-38 03-1A4324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 37% 22% 03-SUT-99-11.0/14.3 Federal Project: SARR-P099(529) A-P099(529) Progress payment No. 13 Payment period ending: 10-20-11 NEHEMIAH CONSTRUCTION INC 12150 TRIBUTARY PT DR. STE120 GOLD RIVER, CA 95670 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,826,238.05 1,365,810.51 2.a. Extra Work 1,179,189.86 422,454.46 b. Adjustment Comp. 11,281.40 5,887.00 3. Materials on Hand 2,451,982.54 -695,661.19 4. Earned Subject to Retention 11,468,691.85 1,098,490.78 5. Mobilization 2,850,000.00 0.00 6. Total Work Completed 11,866,709.31 7. Deductions -32,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,286,691.85 1,093,490.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,093,490.78