Dept. of Trans. PROGRESS Serial No. Contract No. 12-144-09-39 03-1A4324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 52% 37% 03-SUT-99-11.0/14.3 Federal Project: SARR-P099(529) A-P099(529) Progress payment No. 21 Payment period ending: 05-17-12 SAFECO INSURANCE COMPANY P.O. BOX 34670 SEATTLE, WA 98125 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,160,480.97 3,150.00 2.a. Extra Work 4,844,424.22 17,362.11 b. Adjustment Comp. 103,821.46 0.00 3. Materials on Hand 2,718,870.75 4,786.80 4. Earned Subject to Retention 17,827,597.40 25,298.91 5. Mobilization 3,000,000.00 0.00 6. Total Work Completed 18,108,726.65 7. Deductions -23,475.00 22,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 20,804,122.40 47,298.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 47,298.91