Dept. of Trans. PROGRESS Serial No. Contract No. 09-296-14-39 03-1A4614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 54% 35% 03-SUT-99-16.8/23.0 Federal Project: NONE Progress payment No. 08 Payment period ending: 10-20-09 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02421 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,660,432.03 2,474,391.93 2.a. Extra Work 35,116.45 0.00 b. Adjustment Comp. -278,424.75 -282,300.03 3. Materials on Hand 4. Earned Subject to Retention 10,417,123.73 2,192,091.90 5. Mobilization 2,185,000.00 0.00 6. Total Work Completed 12,602,123.73 7. Deductions -20,000.00 -10,000.00 8. a.Contract Retentions -520,856.19 -100,270.63 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,061,267.54 2,081,821.27 10. Reduction Amt to Escrow 11. Payment to Escrow 520,850.00 12. Net Pymt. this Estimate 2,081,821.27