Dept. of Trans. PROGRESS Serial No. Contract No. 09-327-15-13 03-1A4614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 65% 38% 03-SUT-99-16.8/23.0 Federal Project: NONE Progress payment No. 09 Payment period ending: 11-19-09 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02421 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,954,987.88 2,294,555.85 2.a. Extra Work 46,802.38 11,685.93 b. Adjustment Comp. -278,424.75 0.00 3. Materials on Hand 4. Earned Subject to Retention 12,723,365.51 2,306,241.78 5. Mobilization 2,300,000.00 115,000.00 6. Total Work Completed 15,023,365.51 7. Deductions -10,000.00 10,000.00 8. a.Contract Retentions -636,168.28 -115,312.09 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,377,197.23 2,315,929.69 10. Reduction Amt to Escrow 11. Payment to Escrow 636,160.00 12. Net Pymt. this Estimate 2,315,929.69