Dept. of Trans. PROGRESS Serial No. Contract No. 09-357-09-21 03-1A4614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 65% 41% 03-SUT-99-16.8/23.0 Federal Project: NONE Progress payment No. 10 Payment period ending: 12-21-09 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02421 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,015,616.48 60,628.60 2.a. Extra Work 324,929.86 278,127.48 b. Adjustment Comp. -578,395.05 -299,970.30 3. Materials on Hand 92,466.52 92,466.52 4. Earned Subject to Retention 12,854,617.81 131,252.30 5. Mobilization 2,300,000.00 0.00 6. Total Work Completed 15,062,151.29 7. Deductions -15,000.00 -5,000.00 8. a.Contract Retentions -642,730.89 -6,562.61 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,496,886.92 119,689.69 10. Reduction Amt to Escrow 11. Payment to Escrow 642,730.00 12. Net Pymt. this Estimate 119,689.69